Toledo Edison price to compare and competitive offers

How Toledo Edison’s supply rate compares with the offers on the Energy Choice Ohio rate board, what has been moving, what is driving it, and what is scheduled to change.

What is Toledo Edison’s price to compare? It is the price Toledo Edison charges for electricity supply to customers who have not chosen a competitive supplier: 11.26¢ per kWh since October 1, 2026. Delivery charges are the same whoever supplies the electricity.

Price to compare
11.26¢/ kWh
Toledo Edison default service, since October 1, 2026
Lowest offer
8.29¢/ kWh
American Power & Gas, 3-month fixed
Current offers
116
from 33 suppliers on the Energy Choice Ohio rate board
Checked
Nov 202026
3:01 PM Eastern, daily snapshot
Right now

Every current offer against the price to compare

Each dot is one offer on the Energy Choice Ohio rate board, placed by contract length and price. Offers below the dashed line cost less than default service today.

Current offers by contract length, against Toledo Edison’s price to compare

116 offers from 33 suppliers · Energy Choice Ohio · November 20, 2026

7¢8¢9¢10¢11¢12¢13¢14¢3 mo67891218202436Contract length, monthsToledo Edison price to compare11.26¢8.29¢ American Power & Gas, 3 moCurrent offerLowest offerToledo Edison price to compare
GRID SHOPPER7 offers above 14¢ omitted for scale
How it got here

Toledo Edison price to compare history, with the lowest and typical 12-month offers

Daily snapshots of the Energy Choice Ohio rate board. The supply rate moves a few times a year; offers move whenever suppliers reprice.

Lowest offer, average 12-month offer, and Toledo Edison price to compare, May to November 2026

Daily rateboard snapshots · price to compare from default service filings

6¢7¢8¢9¢10¢11¢12¢13¢JunJulAugSepOctNovJun 1 resetOct 1 resetJul 1 resetAvg 12-mo offer11.59¢Toledo Edison price to compare11.26¢Lowest offer8.29¢
GRID SHOPPERLowest offer is the cheapest of any term on that day
View the data
DateLowest offerAvg 12-mo offer
2026-05-207.39¢10.69¢
2026-05-217.39¢10.70¢
2026-05-227.39¢10.63¢
2026-05-237.39¢10.60¢
2026-05-247.39¢10.60¢
2026-05-257.39¢10.60¢
2026-05-267.39¢10.60¢
2026-05-277.39¢10.58¢
2026-05-287.39¢10.58¢
2026-05-297.39¢10.56¢
2026-05-307.39¢10.56¢
2026-05-317.39¢10.56¢
2026-06-017.39¢10.53¢
2026-06-027.39¢10.51¢
2026-06-037.39¢10.51¢
2026-06-047.39¢10.52¢
2026-06-057.39¢10.52¢
2026-06-067.39¢10.53¢
2026-06-077.39¢10.53¢
2026-06-087.39¢10.53¢
2026-06-097.39¢10.56¢
2026-06-107.39¢10.56¢
2026-06-117.39¢10.56¢
2026-06-127.39¢10.54¢
2026-06-137.39¢10.53¢
2026-06-147.39¢10.53¢
2026-06-157.39¢10.53¢
2026-06-167.39¢10.53¢
2026-06-177.39¢10.54¢
2026-06-187.39¢10.60¢
2026-06-197.39¢10.61¢
2026-06-207.39¢10.62¢
2026-06-217.39¢10.62¢
2026-06-227.39¢10.62¢
2026-06-237.39¢10.63¢
2026-06-247.39¢10.60¢
2026-06-257.39¢10.55¢
2026-06-267.39¢10.56¢
2026-06-277.39¢10.57¢
2026-06-287.39¢10.57¢
2026-06-297.39¢10.57¢
2026-06-307.39¢10.55¢
2026-07-017.39¢10.58¢
2026-07-027.39¢10.61¢
2026-07-037.39¢10.60¢
2026-07-047.39¢10.60¢
2026-07-057.39¢10.60¢
2026-07-067.39¢10.60¢
2026-07-077.39¢10.68¢
2026-07-087.39¢10.70¢
2026-07-097.39¢10.78¢
2026-07-107.39¢10.82¢
2026-07-117.39¢10.84¢
2026-07-127.39¢10.84¢
2026-07-137.39¢10.84¢
2026-07-147.39¢10.83¢
2026-07-157.39¢10.85¢
2026-07-167.39¢10.86¢
2026-07-177.39¢10.89¢
2026-07-187.39¢10.87¢
2026-07-197.39¢10.87¢
2026-07-207.39¢10.87¢
2026-07-217.39¢10.89¢
2026-07-227.39¢10.89¢
2026-07-237.39¢10.88¢
2026-07-247.39¢10.90¢
2026-07-257.39¢10.80¢
2026-07-267.39¢10.80¢
2026-07-277.39¢10.91¢
2026-07-287.39¢10.90¢
2026-07-299.09¢10.86¢
2026-07-308.79¢10.86¢
2026-07-318.79¢10.87¢
2026-08-018.79¢10.90¢
2026-08-028.79¢10.90¢
2026-08-038.79¢10.90¢
2026-08-048.79¢10.94¢
2026-08-058.89¢10.96¢
2026-08-068.89¢11.00¢
2026-08-078.99¢10.99¢
2026-08-088.99¢11.03¢
2026-08-098.99¢11.03¢
2026-08-108.99¢11.03¢
2026-08-118.99¢11.02¢
2026-08-128.99¢10.98¢
2026-08-138.99¢10.97¢
2026-08-148.99¢10.97¢
2026-08-158.99¢10.96¢
2026-08-168.99¢10.96¢
2026-08-178.99¢10.96¢
2026-08-188.79¢10.94¢
2026-08-198.79¢10.94¢
2026-08-208.79¢10.94¢
2026-08-218.79¢10.95¢
2026-08-228.79¢10.95¢
2026-08-238.79¢10.95¢
2026-08-248.79¢10.95¢
2026-08-258.79¢10.95¢
2026-08-268.79¢10.96¢
2026-08-278.79¢10.96¢
2026-08-288.79¢10.96¢
2026-08-298.79¢10.95¢
2026-08-308.79¢10.95¢
2026-08-318.79¢10.95¢
2026-09-018.79¢10.95¢
2026-09-028.79¢10.90¢
2026-09-038.79¢10.89¢
2026-09-048.79¢10.90¢
2026-09-058.79¢10.90¢
2026-09-068.79¢10.90¢
2026-09-078.79¢10.90¢
2026-09-088.79¢10.88¢
2026-09-098.79¢10.88¢
2026-09-108.79¢10.89¢
2026-09-118.79¢10.89¢
2026-09-128.79¢10.89¢
2026-09-138.79¢10.89¢
2026-09-148.79¢10.89¢
2026-09-158.79¢10.92¢
2026-09-167.89¢10.93¢
2026-09-177.89¢10.97¢
2026-09-187.89¢11.06¢
2026-09-197.89¢11.07¢
2026-09-207.89¢11.07¢
2026-09-217.89¢11.07¢
2026-09-227.89¢11.07¢
2026-09-237.89¢11.07¢
2026-09-247.89¢11.07¢
2026-09-257.89¢11.07¢
2026-09-267.89¢11.14¢
2026-09-277.89¢11.14¢
2026-09-287.89¢11.14¢
2026-09-297.89¢11.14¢
2026-09-307.89¢11.15¢
2026-10-017.89¢11.21¢
2026-10-027.89¢11.20¢
2026-10-037.89¢11.20¢
2026-10-047.89¢11.20¢
2026-10-057.89¢11.20¢
2026-10-067.89¢11.17¢
2026-10-077.89¢11.17¢
2026-10-087.89¢11.15¢
2026-10-097.89¢11.16¢
2026-10-107.89¢11.17¢
2026-10-117.89¢11.17¢
2026-10-127.89¢11.17¢
2026-10-137.89¢11.16¢
2026-10-147.89¢11.17¢
2026-10-157.89¢11.20¢
2026-10-167.89¢11.20¢
2026-10-177.89¢11.20¢
2026-10-187.89¢11.20¢
2026-10-197.89¢11.20¢
2026-10-207.89¢11.21¢
2026-10-217.89¢11.25¢
2026-10-227.89¢11.23¢
2026-10-237.89¢11.23¢
2026-10-247.89¢11.24¢
2026-10-257.89¢11.24¢
2026-10-267.89¢11.24¢
2026-10-277.89¢11.21¢
2026-10-287.89¢11.19¢
2026-10-297.89¢11.19¢
2026-10-307.89¢11.24¢
2026-10-317.89¢11.26¢
2026-11-017.89¢11.34¢
2026-11-027.89¢11.34¢
2026-11-037.89¢11.35¢
2026-11-047.89¢11.38¢
2026-11-057.89¢11.38¢
2026-11-067.89¢11.38¢
2026-11-077.89¢11.41¢
2026-11-087.89¢11.41¢
2026-11-097.89¢11.41¢
2026-11-107.89¢11.42¢
2026-11-117.89¢11.43¢
2026-11-127.89¢11.44¢
2026-11-137.89¢11.46¢
2026-11-147.89¢11.46¢
2026-11-157.89¢11.46¢
2026-11-168.29¢11.46¢
2026-11-178.29¢11.46¢
2026-11-188.29¢11.47¢
2026-11-198.29¢11.47¢
2026-11-208.29¢11.59¢

One supplier's offers by contract length

September to November 2026

Pick a supplier from the menu to see how each of its contract lengths has been priced, day by day, against the supply rate.
GRID SHOPPER

Share of Toledo Edison residential customers with a competitive supplier

Toledo Edison monthly filings · June 2022 to October 2026, the latest available

60%65%70%75%80%Jul 2022Jan 2023Jul 2023Jan 2024Jul 2024Jan 2025Jul 2025Jan 2026Jul 202673.3%193,359 of 0.26M
GRID SHOPPERUtilities report customer counts several months after the fact
View the data
MonthWith a supplierTotal residentialShare
2022-06190,546276,97068.8%
2022-07189,519276,90768.4%
2022-08185,913276,90667.1%
2022-09183,837277,32366.3%
2022-10185,016277,28266.7%
2022-11186,141277,43267.1%
2022-12183,746277,58766.2%
2023-01181,964277,75065.5%
2023-02179,855277,69764.8%
2023-03178,992262,85268.1%
2023-04179,268263,00468.2%
2023-05186,981262,95371.1%
2023-06189,503262,84572.1%
2023-07190,570262,67472.6%
2023-08191,944262,41973.1%
2023-09192,254262,32873.3%
2023-10194,523262,51374.1%
2023-11200,291262,59776.3%
2023-12201,192263,02676.5%
2024-01200,296263,17876.1%
2024-02199,367263,26075.7%
2024-03198,201263,12575.3%
2024-04197,780262,86375.2%
2024-05198,158262,71775.4%
2024-06202,867262,80577.2%
2024-07203,296262,97077.3%
2024-08200,996263,04476.4%
2024-09199,251263,00575.8%
2024-10198,343263,24475.3%
2024-11202,593263,76276.8%
2024-12202,773264,38776.7%
2025-01201,391264,53676.1%
2025-02199,939264,61275.6%
2025-03198,343264,57775.0%
2025-04196,770264,56674.4%
2025-05198,488264,42275.1%
2025-06198,561264,12875.2%
2025-07195,319264,05974.0%
2025-08192,712263,85173.0%
2025-09190,540263,47472.3%
2025-10188,634263,54971.6%
2025-11187,100263,77470.9%
2025-12188,820264,31171.4%
2026-01189,332264,55571.6%
2026-02188,064264,67471.1%
2026-03186,906264,93070.5%
2026-04185,935264,65070.3%
2026-05197,593264,14874.8%
2026-06201,227264,02176.2%
2026-07198,970264,50175.2%
2026-08197,513264,09774.8%
2026-09195,425263,83074.1%
2026-10193,359263,82973.3%
What is driving it

How Toledo Edison buys default service supply, and at what price

Toledo Edison buys the power behind the price to compare in auctions held ahead of each service period; the latest reaches about three years ahead. The price to compare is the average of what those auctions locked in.

Share of each month’s supply already bought, by auction, and the average price locked in

June 2022 to May 2029 · Toledo Edison default service procurement results, residential

$40$50$60$70$80$90$100$1100%25%50%75%100%$100.10/MWhtodaynot yet boughtJan 2023Jan 2024Jan 2025Jan 2026Jan 2027Jan 2028Jan 2029Avg price bought, $/MWh (left)Supply bought, by auction, Aug 2021 (light) to Jun 2026 (dark), right axis · hover a bar to see which
GRID SHOPPERAuctions stack oldest at the bottom · striped area is supply not yet bought
View the data
Service monthBoughtAvg price ($/MWh)
June 2022100%53.62
July 2022100%53.62
August 2022100%53.62
September 2022100%53.62
October 2022100%53.62
November 2022100%53.62
December 2022100%53.62
January 2023100%53.62
February 2023100%53.62
March 2023100%53.62
April 2023100%53.62
May 2023100%53.62
June 2023100%101.04
July 2023100%101.04
August 2023100%101.04
September 2023100%101.04
October 2023100%101.04
November 2023100%101.04
December 2023100%101.04
January 2024100%101.04
February 2024100%101.04
March 2024100%101.04
April 2024100%101.04
May 2024100%101.04
June 2024100%73.89
July 2024100%73.89
August 2024100%73.89
September 2024100%73.89
October 2024100%73.89
November 2024100%73.89
December 2024100%73.89
January 2025100%73.89
February 2025100%73.89
March 2025100%73.89
April 2025100%73.89
May 2025100%73.89
June 2025100%81.38
July 2025100%81.38
August 2025100%81.38
September 2025100%81.38
October 2025100%81.38
November 2025100%81.38
December 2025100%81.38
January 2026100%81.38
February 2026100%81.38
March 2026100%81.38
April 2026100%81.38
May 2026100%81.38
June 2026100%87.41
July 2026100%87.41
August 2026100%87.41
September 2026100%87.41
October 2026100%87.41
November 2026100%87.41
December 2026100%87.41
January 2027100%87.41
February 2027100%87.41
March 2027100%87.41
April 2027100%87.41
May 2027100%87.41
June 202769%93.53
July 202769%93.53
August 202769%93.53
September 202769%93.53
October 202769%93.53
November 202769%93.53
December 202769%93.53
January 202869%93.53
February 202869%93.53
March 202869%93.53
April 202869%93.53
May 202869%93.53
June 202816%100.10
July 202816%100.10
August 202816%100.10
September 202816%100.10
October 202816%100.10
November 202816%100.10
December 202816%100.10
January 202916%100.10
February 202916%100.10
March 202916%100.10
April 202916%100.10
May 202916%100.10
What is scheduled

The dates that change these numbers

How far ahead Toledo Edison’s supply has been bought. Forecasts and opinions live on the blog.

Supply bought through
May 2029
The June 2026 auction covers service through May 2029
A typical bill

What an average Toledo Edison home uses, and what it costs

Usage from a weather-driven forecast trained on Toledo Edison’s history; bills from Toledo Edison’s current tariff. Supply is the part a competitive offer replaces; delivery is the same for everyone.

October 2026
Estimate
$125
639 kWh · 7% above normal
Supply $72Delivery $53
November 2026
Forecast
$131
671 kWh · 7% below normal
Supply $76Delivery $55
December 2026
Forecast
$163
847 kWh · at normal
Supply $95Delivery $67

Daily usage forecast for an average Toledo Edison home, next 10 days

Dashed line is normal for the date. Bars above it are hotter or colder days than usual.

0102030Nov 18 · 22 kWh (normal 24)Nov 18Nov 19 · 21 kWh (normal 24)Nov 19Nov 20 · 20 kWh (normal 24)Nov 20Nov 21 · 22 kWh (normal 24)Nov 21Nov 22 · 22 kWh (normal 25)Nov 22Nov 23 · 22 kWh (normal 24)Nov 23Nov 24 · 25 kWh (normal 24)Nov 2425 kWhNov 25 · 25 kWh (normal 24)Nov 25Nov 26 · 25 kWh (normal 25)Nov 26Nov 27 · 23 kWh (normal 24)Nov 27Normal for the date
GRID SHOPPERForecast updated twice daily
View the data
DateForecast (kWh)Normal (kWh)
2026-11-182224
2026-11-192124
2026-11-202024
2026-11-212224
2026-11-222225
2026-11-232224
2026-11-242524
2026-11-252524
2026-11-262525
2026-11-272324
Sources
Offers from the Energy Choice Ohio rate board, snapshotted daily. Price to compare and auction results from Toledo Edison default service filings. Delivery rates from Toledo Edison’s residential tariff. Customer counts from Toledo Edison’s monthly filings. Checked November 20, 2026.